No construction work or roadway closures will occur on Monday, September 7, 2026, due to the Labor Day holiday. Work resumes Tuesday, September 8. 

Activity

Crews continue backfilling and importing dirt as part of ongoing site earthwork at the Advanced Water Purification Facility (AWPF) site. 

Soil nail retaining wall construction continues, including installation of the next wall lift, hanging rebar, and installing fencing. Crews expect to begin prepping to shoot the permanent wall facing by the end of the week. 

Traffic Impacts 

Heavy trucks and equipment will continue to enter and exit the site throughout the week. 

Construction is a dynamic process. This information and the project schedule are subject to change due to weather, field conditions, and other factors.

Contact Us 

If you have questions or would like additional details about this work, please contact the Project Outreach Team at (818) 245-4440. 

Want to learn more about Pure Water construction activities in Agoura Hills? Sign-up for Agoura Hills construction updates below! 

A construction site featuring trucks and heavy machinery, with earth being moved and a clear blue sky above.

Sign Up for Agoura Hills Construction Updates

There was a problem saving your submission. Please try again later.
Please wait while your submission is being saved...
Thank you, your submission has been received.

Past Construction Updates

Join our mailing list